Projects
A selection of substation, underground cable, protection & SCADA modernisation, and power-quality projects delivered across Saudi Arabia for Aramco, Saudi Electricity (SE), and the National Water Company.
Expansion of 33kV Switchgear at PSS-3 (SPARK) and Construction of New 33kV Smart Metered Ring MSSD
Rehabilitation of the existing 33kV switchgear, replaced with a new switchgear design to enhance overall substation performance, and replacement of the existing protection relays with new, modern-generation relays across several substations.
Replacement of 110kV LPOF Underground Cable Circuits JMC-TR01-TR02 & TTC-AL03-AL04
Full design for the replacement cable circuits including cable routing and calculations across several substations — P&C panel design, relay settings, earthing design, and cable schedules.
Replacement of 132kV LPOF Underground Cable Circuits 8025-9015B, 8166-9004 & 8009-8072 in COA
Full design for 132kV cable circuits including cable routing and calculations across several substations in Riyadh — P&C panel design, relay settings, earthing design, and cable schedules.
Construction of New 132/33kV Mughyira Substation
Construction of a new 132/33kV substation including the entire scope of work for electrical, civil, mechanical, and architectural designs.
Construction of New 132/33kV Royal Commission Eastern Substation
Construction of a new 132/33kV substation including the entire scope of work for electrical, civil, mechanical, and architectural designs.
Construction of 33kV STATCOM with 20MVAR at RCU-E Substation
Construction of new 33kV STATCOM designs including the entire scope of work for electrical, civil, and mechanical designs.
Retirement of Existing Wooden Poles 115kV OHTL Between Khurais 380 BSP and RWPS 3C (LV6) Substations
Addition of a 115kV GIS bay and construction of a new 33kV building including the entire scope of work for electrical, civil, mechanical, and architectural designs.
Reinforcement of New Zallum 33/13.8kV Substation
Replacement of the 33/13.8kV substation with new 33kV switchgear including the entire scope of work for electrical, civil, mechanical, and architectural designs.
Rehabilitation of Air Defence (ADF) Substations in Jeddah
Rehabilitation of the existing 13.8kV switchgear, replaced with a new switchgear design to enhance overall substation performance.
Installation, Design and Engineering Services for Installation of MV Circuit Breakers in WOA and NWOA
Rehabilitation of the existing 13.8kV switchgear, replaced with a new switchgear design to enhance overall substation performance.
Replacement of 33/13.8kV Power Transformers at S/S Nos. 7040, 7041, 7781 & 7904 by 20 MVA 33/13.8kV Power Transformers, and Protection & SCADA Requirements for S/S 7218
Replacement of the old power transformers with new units to enhance and upgrade overall substation capacity.
Replacement of Existing 33kV Old Cable, and Protection, SCADA and Communication Modification in 13 Substations in Riyadh
Full design for 33kV cables including cable routing and calculations across several substations in Riyadh — P&C panel design, relay settings, earthing design, and cable schedules.
Replacement of Existing 110kV Old Cable, Protection, SCADA and Communication Modification in 4 Substations in Madinah Area
Replacement of the existing protection relays with new, modern-generation relays across several substations.
Refurbishment of 33kV Ayban, Muhayil and Samatah Substations in Jizan Area
Rehabilitation of the existing switchgear, replaced with a new switchgear design to enhance overall substation performance, and replacement of the existing protection relays with new, modern-generation relays across several substations.
Replacement of Old Switchgear with New Main Switchgear
Rehabilitation of the existing 13.8kV switchgear, replaced with a new switchgear design to enhance overall substation performance.
Replacement of Old Switchgear with New Main Switchgear — STPPH4
Rehabilitation of the existing 13.8kV switchgear, replaced with a new switchgear design to enhance overall substation performance.
Replacement of Electro-Mechanical Relays at S/S 8703 with Numerical Relays Including Required Modifications
Replacement of the existing protection relays with new, modern-generation relays.
Replacement of Old Protection Relays with New IED Devices at OMR, ANS, RDS, RWD and TTC Substations
Replacement of the existing protection relays with new, modern-generation relays across several substations.
Have a project in mind?
Tell us about your requirements and we'll respond with a scoped proposal.